CBA-IPI Method Description
Ø“When the team has
achieved full coverage of the CMM ... the rating process may begin by
rating each goal for each KPA within the assessment scope …
If the team decides that there are no significant weaknesses
that have an impact on a goal, it is rated satisfied.”
Ø“For a KPA to be rated
satisfied, all goals for the KPA must be rated satisfied.”
Ø“For a particular
maturity level rating to be achieved, all KPA’s within and below a
given maturity level must be satisfied.”
ØAn organization must
satisfy all the GOALS of Maturity Levels